Why Wetland and Drainage Laws Matter

Before a shovel ever hits the ground, Michigan developers must evaluate how water, soil, and topography interact with the land. Wetlands, drains, and floodplains aren’t just environmental features — they’re regulatory triggers. Overlooking them can delay or kill an otherwise profitable deal.


Example: A builder in Ottawa County purchased 15 acres for a subdivision. A hidden wetland complex required a state permit and a 30-foot setback, reducing buildable area by 25%.


The Core Regulations — Michigan NREPA

Michigan regulates wetlands and surface waters through the Natural Resources and Environmental Protection Act (NREPA):

  • Part 301 — Inland Lakes and Streams: Covers dredging, filling, or altering water bodies.

  • Part 303 — Wetlands Protection: Governs draining, filling, or construction within regulated wetlands.

  • Part 91 — Soil Erosion and Sedimentation Control: Requires permits for any disturbance over 1 acre or within 500 feet of water.


Enforcement: The Michigan Department of Environment, Great Lakes, and Energy (EGLE) oversees these permits, often in partnership with county conservation districts.


What Counts as a “Wetland” in Michigan?

Under Part 303, a wetland is any area saturated long enough to support water-loving vegetation — even if it looks dry most of the year.

EGLE regulates wetlands that are:

  • Within 1,000 feet of an inland lake, pond, or stream, or

  • 5 acres or larger in size, or

  • Ecologically connected to a regulated water body


Pro Tip: Small or “isolated” wetlands under 5 acres may still require permits if EGLE deems them critical to drainage or habitat.


Typical Setback Requirements

Wetland and water setbacks vary by township and zoning district, but generally include:

  • 25–50 feet from the edge of regulated wetlands

  • 50–100 feet from lakes or streams

  • 10–25 feet from stormwater detention basins


Example: Fruitport Township requires a 50-foot buffer from wetland boundaries and prohibits new septic systems within 100 feet of any watercourse.


Drainage Law: County Drains and Easements

Michigan’s Drain Code of 1956 (Public Act 40) gives county drain commissioners broad authority over surface-water management.

Developers must:

  • Get approval for stormwater systems discharging to county drains

  • Dedicate drainage easements for maintenance access

  • Size detention basins to handle 100-year storm events (per county design manual)


Important: Drain easements can restrict driveway placement, grading, or even building footprints — always check recorded plats and surveys.


Wetland Delineation and Permitting

Before construction, hire a certified wetland delineator to flag and map any potential wetlands.

Permit steps:

  1. Pre-application meeting with EGLE or local agency

  2. Submit site plan and wetland delineation report

  3. Receive joint permit (if under Part 301 & 303)

  4. Public notice and potential comment period

  5. Approval with conditions or mitigation requirements


Timeline: 60–120 days depending on project complexity.


Wetland Mitigation Options

If unavoidable impacts occur, developers must replace or enhance wetlands elsewhere.

Options include:

  • On-site mitigation: Create new wetlands on your property

  • Off-site mitigation: Restore wetlands nearby

  • Mitigation banking: Purchase credits from a state-approved wetland bank


Michigan Example: The Ottawa County Wetland Mitigation Bank allows developers to buy credits for about $75,000 per acre to satisfy Part 303 requirements.


Local Drainage and Stormwater Ordinances

Most West Michigan municipalities (Muskegon, Holland, Grand Haven, etc.) enforce stormwater management ordinances requiring:

  • Detention/retention basins

  • Oil and sediment traps

  • Green infrastructure (rain gardens, permeable pavement)

  • Post-construction maintenance agreements


Pro Strategy: Coordinate site engineers early — plan stormwater design before zoning submission to avoid redesign costs.


Penalties and Common Violations

  • Filling wetlands without a permit → fines up to $10,000/day

  • Blocking county drains → county-ordered restoration and civil penalties

  • Poor soil erosion control → stop-work orders and municipal enforcement


Case Study: In 2021, a West Michigan builder was fined $40,000 after grading over 2 acres of wetland buffer without authorization — all avoidable with early EGLE coordination.


Final Thoughts

Michigan’s wetland and drainage laws aren’t barriers — they’re blueprints for responsible, resilient development. When you understand how EGLE, counties, and zoning interact, you can design smarter sites, protect your investment, and build goodwill with local planning boards.


If you’re evaluating land for development in West Michigan, I can help coordinate environmental due diligence, connect you with trusted engineers, and navigate the permit process from feasibility to final approval.


Because successful development isn’t just about where you build — it’s about knowing what’s under and around your land.



West Michigan Realtor Dave Manley

Written by Dave Manley — West Michigan Realtor® offering straight-talk real estate guidance and practical insight for buyers and sellers.

616-402-3595


Comments


bottom of page